Our new Education Building will house a fellowship area, kitchen, full restrooms (including showers) and two offices on the first floor. The second floor will consists of classrooms and restrooms.
Progress reports:
01/08/2010 Footers have been poured and the Marge house is
being prepared to move; possibly Wednesday or Thursday, depending on the
weather.
(Click on photos for larger view)
01/21/2010 Marge's house has been moved. (Click on photos for larger view)
01/27/2010 Foundation walls are going
up. (Click on photos for larger view)
03/10/2010 Metal siding going up. (Click on photos for larger
view)
03/27/2010 Church work day. Most of 1st floor interior walls went up.
04/3/2010 Church work day.
11/21/2010 Held first Sunday potluck in the building!! See pictures below!
04/03/2011 Educational Building is complete!